Project

Project Details

Westpac PNG’s new occupancy fitout of two levels at Harbourside West Building in Port Moresby.

ECM Provides electrical services including:

• New Systimax Data Centre
• New Kohler 165kVA essential services back up generator with remote monitoring
• 2500L Bulk Diesel storage including remote fill station, electronic gauging and remote monitoring
• 125kW UPS system integration
• Treasury, Dealership, meeting and office rooms
• Horizontal and backbone Communication system
• Essential Services and UPS distribution boards
• Submain reticulation
• Modification to existing building services switchboards
• General electrical and lighting systems
Location: Port Moresby
Head Contractor: Zone (PNG) Ltd
Consultant: M&E Partnership